While owning the land first may seem to eliminate one factor from the equation of custom building, that lot has already been paid for and dozens of other factors have already been ‘fixed’ before you even sit down to begin designing your custom home. The cost of the site must be honestly reflected; the home designed to maximize the potential of the site, not to be an afterthought as it would be on a developer’s site; and you must be able to hold your designer and builder to a schedule as the selection process unfolds.
Underwrite the land before you underwrite the house
As with the purchase of a home, the lot was purchased years ago for its view or for its purchase price. As such, it has rarely been scrutinized by a builder’s eye. A site analysis similar to that a lender would perform to approve a loan for a home purchase is necessary prior to commencing the design of a custom home.
Due diligence that changes the number
- A current survey with topographic contours, not a plat from the original subdivision.
- Soil borings or a geotechnical letter where slopes exceed roughly fifteen percent, or where fill is suspected.
- Septic suitability and repair area, or a written availability letter from the sewer authority.
- Well yield data from neighboring parcels if public water is not at the property line.
- Recorded easements, setbacks, stream buffers, and any private road maintenance agreement.
Each of these ‘costs’ a few hundred dollars to a few thousand dollars. But then transferring these ‘costs’ to the construction contract as change orders means they are priced at an even greater cost to the homeowner.
Budget in three buckets, not one
Site development should be accounted for in a separate ‘bucket’ to house construction and soft costs. The combined cost of these three factors as a square footage cost to a house will vary for two identical houses on different sites, often by as much as six figures. And of all these variables site work is the most uncertain to estimate. So, require a separate contingency for site work rather than trying to take it from the finishes.
| Site condition | Engineering typically required | Primary cost driver | Schedule effect |
| Flat infill lot, utilities at street | Minimal, erosion control plan | Utility tap and impact fees | Little to none |
| Moderate slope, public water | Grading plan, retaining wall design | Excavation, walls, driveway base | Two to four weeks of added sitework |
| Steep mountain parcel | Geotechnical report, structural foundation design | Rock removal, engineered foundations, access road | One to three months |
| Rural acreage, no utilities | Septic design, well permit, power extension | Linear cost of service extension | Utility company lead times, often the long pole |
Let the site dictate the floor plan
Typically plans are chosen from a designer’s catalog and depict a flat, rectangular building site with the street on one side. Establish the buildable envelope, driveway approach and solar orientation first and then select a plan or have one drawn that fits within these constraints.
Modify a stock plan or start from scratch
Changes such as a change to an elevation, garage or foundation type are considered modifications and are generally more cost effective to redesign rather than amend. If your lot sits on a grade, it is worth talking early with Asheville custom home builders, since many regional firms keep designers in house and tend to be very good at site specific designs. However, even with the best designers, there are often many amendments especially to the structural and M&E plans.
Lock design choices against a selections schedule
Be cautious of Allowances! An allowance is nothing more than a placeholder for a selection that the client will make at a later date. More often than not the selection will end up costing so much more than the original allowance and it should be converted to a specified product as early as possible in the drawing development process.
- Specify windows, exterior cladding, and roofing before permit submission, since they affect energy calculations and inspections.
- Finalize cabinetry layouts and appliance models before mechanical rough-in, because venting and outlets follow them.
- Choose plumbing fixtures before rough-in, and tile before the waterproofing scope is priced.
- Defer only paint colors, light fixtures, and hardware, which carry no structural consequence.
Build the schedule backward from permits and lead times
The duration of the physical build can be the least unknown element of the total timeframe. Typically the design and engineering can take between three and six months, the permit process 4-12 weeks (depending on if there is a separate grading permit and if it is issued by the same jurisdiction as the building permit) and then the actual build can take between 9-16 months for a good custom home design.
What to order early
Windows, structural steel, specialty roofing and certain appliances such as, Sub-Zero and Wolf units are generally considered to have very long lead times. It is best to place orders for these items during permit review and verify that the construction loan allows for the deposit of materials stored off-site. Note that a framing crew waiting for a window delivery to arrive would cost more than the storage of the item(s).
Build in float for weather and for expected delays due to inspection backlog. Then each month identify where you are on the critical path of your custom home. Even lots purchased on an intuited basis can make for excellent custom homes if the lot is adequately analyzed prior to the purchaser spending the lot funds.